Free Excavation & Earthmoving SWMS Template

Covers service location, machine excavation, trench support and backfill for bulk earthworks and trenching. No signup, no email required.

How is this template compliant?

Every state and territory publishes its own guidance on what a SWMS should cover. We've taken the highest-common-denominator approach: for each required element — job steps, hazards, controls, PPE and the rest — we've built this template to the most complete state recommendation for that category, not the lowest. The result is a single template that meets the bar in every state, rather than one written for a single state and hoping it holds up elsewhere.

Applicability

This template covers excavation & earthmoving work that falls under one or more high-risk construction work (HRCW) categories, where a SWMS is mandatory before work starts. It's written for use in every Australian state and territory — under the WHS Regulations in most jurisdictions, and the equivalent OHS Regulations in Victoria.

Work in or near a shaft or trench deeper than 1.5 metres Work in an area with movement of powered mobile plant Work on or near a road, railway or other traffic corridor in use by traffic other than pedestrians Work on or near pressurised gas distribution mains or piping Work on or near chemical, fuel or refrigerant lines Work in or near a confined space Work on or near energised electrical installations or services Work in an area that may have a contaminated or flammable atmosphere Work in or near water or another liquid with a risk of drowning

Document preview

Excavation & Earthmoving SWMS Template

Fill it out automatically with a meticulous AI

Complete an in-depth risk assessment for this SWMS in minutes

  • Instant sign in
  • No spam emails
  • Export PDF/Word
Fill out this SWMS for Free

Fill it out manually

Download the static file and fill it in yourself.

20 high risk activities, hazards, and controls unique to Excavation & Earthmoving for a SWMS

This template is built specifically for bulk earthworks, trenching and site excavation — not a generic SWMS with the trade name swapped in. Here's what's pre-filled.

Trench or excavation collapse

  • Protective system (shoring, battering or benching) designed for depth and soil type
  • No entry to excavations over 1.5 metres without a protective system
  • Spoil and materials kept back from the excavation edge
  • Daily inspection by a competent person before entry

Contact with underground services during machine excavation

  • Dial Before You Dig search completed and results on site
  • Hand potholing within 500mm of any marked service before machine digging
  • Standby spotter during all machine excavation near services

Powered mobile plant movement (excavators, trucks, loaders)

  • Exclusion zones maintained around operating plant
  • No ground personnel inside the machine swing radius
  • Reversing alarms fitted and spotters used for all reversing movements

Fall into an open excavation

  • Barricades or hoarding placed around open excavations
  • Covers fitted over unattended holes and trenches
  • Edge protection used where the public or other trades are nearby

Confined space hazards in deep or enclosed excavations

  • Excavation assessed for confined space classification before entry
  • Atmospheric testing conducted before entry into deep or enclosed excavations
  • Confined space permit and standby person used where required
  • Rescue plan and equipment in place before entry

Contact with energised underground electrical cables

  • Dial Before You Dig results cross-checked with a cable locator before digging near marked electrical services
  • Excavation near known electrical services treated as live until proven isolated
  • Hand digging only within the exclusion zone of marked electrical services
  • Standby person present while electrical services are exposed

Strike on pressurised gas mains or piping

  • Gas authority notified and asset owner consulted before excavating near gas mains
  • Hand exposure only within the tolerance zone of marked gas services
  • Work stopped and area evacuated immediately if a gas line is struck or damaged

Contaminated or flammable atmosphere in excavations

  • Atmosphere tested before entry into low-lying or enclosed excavations
  • Excavations in known contaminated ground assessed before work starts
  • No ignition sources permitted where a flammable atmosphere is possible

Rollover of excavators or loaders on unstable or sloping ground

  • Ground conditions assessed for load-bearing capacity and slope before machine access
  • Machines operated within manufacturer-rated slope limits
  • Batters and stockpiles kept clear of machine travel paths
  • ROPS-fitted machines used with seatbelts worn at all times

Struck by plant during truck loading and spotting

  • Exclusion zone maintained around loading trucks
  • Spotter used for all truck positioning and loading movements
  • Truck drivers remain in the cab or a designated safe area during loading

Manual handling of shoring, pipes and fittings

  • Mechanical lifting or machine assistance used for heavy shoring components and pipe sections
  • Team lifts used for awkward or heavy items
  • Materials staged close to the point of use to limit carry distance

Water ingress and drowning risk in flooded excavations

  • Dewatering pumps used to remove standing water before entry
  • Excavation re-inspected for wall stability after dewatering
  • No entry permitted into water-filled excavations

Undermining of adjacent structures, footpaths or services

  • Excavation depth and proximity to adjacent structures assessed before digging
  • Engineer consulted where excavation may undermine footings or structures
  • Ground movement monitored near existing structures during excavation
  • Temporary support installed where an undermining risk is identified

Overhead powerline contact with excavator boom or tipper truck

  • Overhead clearance checked and no-go zones established before machine setup
  • Tipper truck tray lowered before moving near overhead lines
  • Spotter used when machines operate near powerlines

Traffic and public interface hazards adjacent to roadways

  • Traffic management plan implemented for work adjacent to roadways
  • Signage, barriers and delineation used to separate the public from the excavation
  • Trained traffic controllers used where required by the traffic management plan

Noise exposure from excavators, compactors and machinery

  • Hearing protection worn for all high-noise plant operation
  • Task rotation used to limit individual exposure duration
  • Machines maintained to manufacturer specification to limit noise output

Whole-body vibration from prolonged machine operation

  • Seat suspension and machine maintenance checked regularly
  • Operator hours on vibration-prone machines rotated between crew
  • Breaks scheduled during extended machine operation

Silica dust exposure from dry excavation, rock breaking or crushing

  • Water suppression used during dry excavation, rock breaking or crushing
  • P2 respirator worn where dust suppression is not sufficient
  • Dust-generating tasks scheduled away from other workers where practical

Heat stress and UV exposure working outdoors

  • Hydration breaks scheduled during hot conditions
  • Sun-protective clothing, hat and sunscreen used for outdoor work
  • Shade provided during breaks
  • Work rescheduled to cooler parts of the day where practical

Slips, trips and falls on uneven or spoil-covered ground

  • Site access routes kept clear of spoil, materials and equipment
  • Appropriate footwear worn for uneven ground conditions
  • Excavated material stockpiled away from walkways and access points

Frequently asked questions

What is a SWMS?

A Safe Work Method Statement (SWMS) is a legally required document for high-risk construction work. It sets out the job steps, the hazards involved, and the controls you'll use to manage them before work starts.

Do I need a SWMS for bulk earthworks, trenching and site excavation?

If the work falls into one of the 18 high-risk construction work categories under the WHS Regulations, a SWMS is mandatory before work can start. This template is pre-mapped to the categories that typically apply to excavation & earthmoving work of this kind.

Is this template really free?

Yes. Join with your Google account in 10 seconds, no card required, and it's saved to your account ready to customise, publish and get signed by your crew online.

Can I use this template as-is?

Treat it as a starting point, not a finished document. Every site is different — add your site-specific hazards, confirm the controls suit the actual job, and have it reviewed before workers sign it.

This template is a starting point only. Review and adapt it for your actual site conditions before use — it is not a substitute for a competent person's own risk assessment.